Matthew and Mark work for AMG, and want to do some aggregate planning using Level Production without Backorders for the manufacturing of brake calipers for

Matthew and Mark work for AMG, and want to do some aggregate planning using "Level Production without Backorders" for the manufacturing of brake calipers for Mercedes Benz S63 sedans. They figure the front brake calipers take 8 hours to forge and assemble while the rear calipers take 5 hours to forge and assemble. They pay their people $24.00 per hour and it costs them $900.00 to hire and $1,300 to fire each employee. They currently employ 3 people and have 129 front calipers in inventory and 113 rear calipers in inventory. Inventory carrying costs are $7.00 per labor hour. Assume 40 hours per week and 4 weeks per month. Please disregard rounding errors and select the closest answer.

The following is the 6 month demand forecast in units:

Month

1

2

3

4

5

6

Front Calipers

200

750

330

550

240

180

Rear Calipers

230

730

340

500

250

220

You will need to first figure what the level production amount will be using the following information over 6 periods:

1 2 3 4 5 6

Cumulative Demand

Beginning Inventory (Constant using the inventory levels given)

Total Cumulative Production

Monthly Production

Use the following model to construct your analysis:

1 2 3 4 5 6

Beginning Inventory

Demand

Production

Ending Inventory

Hire Costs

Fire Costs

Wage Costs

Inventory Costs

Total Costs

Each Question is worth 2 points, for a total of 10 points.

1. What is the cumulative demand for all periods in labor hours?

A. 28,970

B. 24,810

C. 27,080

D. 29,350

2. What is the level production amount in labor hours?

A. 5,089

B. 4,667

C. 5,511

D. 4,266

3. How many employees will they need to hire (or fire)?

A. Fire 2

B. Hire 32

C. Hire 26

D. Hire 29

4. What is the hiring (or firing) cost in Period 1?

A. $21,600

B. $28,800

C. $23,400

D. $26,100

5. What is the total cost for implementing this plan?

A. $917,672

B. $760,599

C. $687,699

D. $777,862

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started