McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2009 and completed in 2010. Cost and other

McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2009 and completed in 2010. Cost and other data are presented below:

2009 2010

Costs inccured during the year $1,500,000 $1,300,000

Estimated costs to complete $1,200,000 -0-

Billings during the year $1,200,000 $1,300,000

Cash Collections during the year $1,000,000 $1,500,000

Assume that McCombs uses the percentage-of-completion Method for revenue recognition

1 ) what is the amount of gross profit recognized during 2009 and 2010

2) Prepare all journal entries to record costs, billings, collections, and profit recognition.

Assume that McCombs uses Completed Contract Method

1) wha is the amount of gross profit recognized during 2009 and 2010

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing An International Approach

Authors: Wally Smieliauskas, Amy Kwan, Kathleen Cogliano, Catherine Barrette

8th Canadian Edition

ISBN: 1259451275, 978-1259451270

More Books

Students also viewed these Accounting questions