McCoy Company McCoy Company has the following information available for October when 3,500 units were produced. Standards: Material: 3.5 pounds per unit @ P4.50 per
McCoy Company
McCoy Company has the following information available for October when 3,500 units were produced.
Standards:
Material: 3.5 pounds per unit @ P4.50 per pound
Labor: 5.0 hours per unit @ P10.25 per hour
Actual:
Material purchased: 12,300 pounds @ P4.25
Material used: 11,750 pounds
Labor:17,300 direct labor hours @ P10.20 per hour
Required:
1.Refer to McCoy Company. What is the labor rate variance?
2.Refer to McCoy Company. What is the labor efficiency variance?
3.Refer to McCoy Company. What is the material price variance (based on quantity purchased)? MPV = (AP - SP) * AQP
4.Refer to McCoy Company. What is the material quantity variance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 Labor Rate Variance LRV This is the difference between the actual labor rate and the standard labor rate multiplied by the actual hours worked The f...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started