McGee Carpet and Trim installs carpet in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several
McGee Carpet and Trim installs carpet in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table.
Activity | Time (days) | Immediate Predecessor(s) | |||||
---|---|---|---|---|---|---|---|
a | m | b | |||||
A | 4 | 5 | 8 | ||||
B | 4 | 5 | 6 | ||||
C | 1 | 2 | 3 | ||||
D | 6 | 7 | 8 | C | |||
E | 3 | 5 | 7 | B, D | |||
F | 2 | 3 | 4 | A, E | |||
G | 6 | 10 | 15 | A, E | |||
H | 11 | 12 | 13 | F | |||
I | 5 | 7 | 9 | G | |||
J | 13 | 15 | 17 | C | |||
K | 4 | 8 | 12 | H, I |
a) Based on the activity time estimates, the expected times and variance for each of the activities are:(Round your responses to two decimal places.)
Activity | Expected Time | Variance | |
---|---|---|---|
A | enter your response here | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started