MegaCorp budgeted 5,000 units of production, with total overhead costs budgeted at $50,000. Actual production was 6,000
Fantastic news! We've Found the answer you've been seeking!
Question:
MegaCorp budgeted 5,000 units of production, with total overhead costs budgeted at $50,000. Actual production was 6,000 units, and actual overhead costs amounted to $55,000. Calculate the overhead spending variance and the overhead efficiency variance.