Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the companys estimator and
Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the companys estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as the removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $2.50 to determine the bid price. Since our average cost is only $2.235 per square foot, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.
To shed light on this controversy, the company initiated an activity-based costing study of all of its costs.
Data from the activity-based costing system follow:
Activity Cost Pool | Activity Measure | Total Activity | |
---|---|---|---|
Removing asbestos | Thousands of square feet | 800 | thousand square feet |
Estimating and job setup | Number of jobs | 500 | jobs |
Working on nonroutine jobs | Number of nonroutine jobs | 100 | nonroutine jobs |
Other (organization-sustaining costs and idle capacity costs) | None |
Note:
The 100 nonroutine jobs are included in the total of 500 jobs.
Both nonroutine jobs and routine jobs require estimating and setup.
Resource | Costs |
Wages and salaries | $ 317,000 |
---|---|
Disposal fees | 712,000 |
Equipment depreciation | 97,000 |
On-site supplies | 55,000 |
Office expenses | 220,000 |
Licensing and insurance | 420,000 |
Total cost | $ 1,821,000 |
Removing Asbestos | Estimating and Job Setup | Working on Nonroutine Jobs | Other | Total | |
---|---|---|---|---|---|
Wages and salaries | 50% | 15% | 20% | 15% | 100% |
Disposal fees | 60% | 0% | 40% | 0% | 100% |
Equipment depreciation | 50% | 10% | 15% | 25% | 100% |
On-site supplies | 60% | 25% | 15% | 0% | 100% |
Office expenses | 10% | 40% | 15% | 35% | 100% |
Licensing and insurance | 30% | 0% | 60% | 10% | 100% |
Using the information above, you are required to complete the following:
Perform the first-stage allocation of costs to the activity cost pools.
Compute the activity rates for the activity cost pools.
Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system.
A routine 1,000-square-foot asbestos removal job.
A routine 2,000-square-foot asbestos removal job.
A nonroutine 2,000-square-foot asbestos removal job.
Flag question: Question 1
Question 131 pts
Section 1 | Perform the first-stage allocation of costs to the activity cost pools
Complete the following:
Create a table similar to or exactly like the one shown below.
Input the information and the correct data directly into the table where appropriate.
Please Note |
You are also required to show your work for each of the sections below.
Provide the correct data for each activity (worth 7 points).
Activities | Removing Asbestos | Estimating and Job Setup | Working on Nonroutine Jobs | Other | Total |
Wages and Salaries | $ | $ | $ | $ | $ |
Disposal Fees | |||||
Equipment Depreciation | |||||
On-site Supplies | |||||
Office Expenses | |||||
Licensing and Insurance | |||||
Total Cost | $ | $ | $ | $ | $ |
Show your work (worth 24 points):
You are also required to show your work (provide calculations and the data used to obtain your response(s) to receive full credit) for each of the sections below.
Example: For each activity include the activity, the data (calculation methods), and the data used to obtain your response (see the example below for "Wages and Salaries."
How you can show your work directly into Canva:
Type the information in the space provided.
Create a table and include all required information.
Make sure all information is legible and formatted correctly to display data.
Bold and underscore the data total placed in your table.
Example: If the data total under "Wages and Salaries" for "Removing Asbestos" is $2,319; this would be bolded and underscored.
If you decide to upload this information in a separate document, please make sure it is typed, appropriately aligned, and all necessary information is included.
Only upload MS Word or PDF documents (Do not upload any format of google documents to this file).
Any inaccessible responses will automatically be scored 0% (no exceptions).
Wages and Salaries: Removing asbestos = Estimating and Job Setup = Working on Nonroutine Jobs = Other = |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started