Question

1 Approved Answer

Mercury, Inc., produces cell phones at its plant in Texas. In recent years, the companys market share has been eroded by stiff competition from overseas.

Mercury, Inc., produces cell phones at its plant in Texas. In recent years, the companys market share has been eroded by stiff competition from overseas. Price and product quality are the two key areas in which companies compete in this market.

A year ago, the companys cell phones had been ranked low in product quality in a consumer survey. Shocked by this result, Jorge Gomez, Mercurys president, initiated an intense effort to improve product quality. Gomez set up a task force to implement a formal quality improvement program. Included on this task force were representatives from the Engineering, Marketing, Customer Service, Production, and Accounting departments. The broad representation was needed because Gomez believed that this was a companywide program and that all employees should share the responsibility for its success.

After the first meeting of the task force, Holly Elsoe, manager of the Marketing Department, asked John Tran, production manager, what he thought of the proposed program. Tran replied, I have reservations. Quality is too abstract to be attaching costs to it and then to be holding you and me responsible for cost improvements. I like to work with goals that I can see and count! Im nervous about having my annual bonus based on a decrease in quality costs; there are too many variables that we have no control over.

Mercurys quality improvement program has now been in operation for one year. The companys most recent quality cost report is shown below.

Mercury, Inc.
Quality Cost Report
(in thousands)
Last Year This Year
Prevention costs:
Machine maintenance $ 200 $ 150
Training suppliers 4 10
Quality circles 26 90
Total prevention cost 230 250
Appraisal costs:
Incoming inspection 45 20
Final testing 150 90
Total appraisal cost 195 110
Internal failure costs:
Rework 100 60
Scrap 60 45
Total internal failure cost 160 105
External failure costs:
Warranty repairs 60 20
Customer returns 250 88
Total external failure cost 310 108
Total quality cost $ 895 $ 573
Total production cost $ 4,100 $ 4,500

As they were reviewing the report, Elsoe asked Tran what he now thought of the quality improvement program. Tran replied. Im relieved that the new quality improvement program hasnt hurt our bonuses, but the program has increased the workload in the Production Department. It is true that customer returns are way down, but the cell phones that were returned by customers to retail outlets were rarely sent back to us for rework.

Required:

1. Expand the companys quality cost report by showing the costs in both years as percentages of both total production cost and total quality cost. (Round your percentage answers to 1 decimal place (i.e 0.1234 should be entered as 12.3).)

image text in transcribed

Please include the way to find the percentages.

Mercury, Inc Quality Cost Report (in thousands) Last Year This Year Percentage of Percentage of Percentage of Percentage of Amount Total Production Amount Total Production Total Qual Total Quality Cost Total Qual Total Quality Cost Cost Cost Prevention costs 200 4 26 230 4.91 % 224 | % | Machine maintenance Training suppliers Quality circles 150 90 4.9 22.4 250 0.0 0.0 Total prevention costs Appraisal costs Incoming inspection Final testing 45 150 195 20 90 110 Total appraisal costs 0.0 0.0 0.0 0.0 Internal failure costs 100 60 160 60 45 105 Rework Scrap Total internal failure costs External failure costs 0.0 0.0 0.0 0.0 60 250 310 895 $4,100 Warranty repairs 20 Customer returns Total external failure costs Total quality cost Total production cost 108 573 $4,500 0.0 0.0 0.0 0.0 0.0 4.9 22.4 0.0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems

Authors: Patrick R. Wheeler, Ulric J. Gelinas, Richard B. Dull, Dull Gelinas Wheeler

International 10th Edition

017035539X, 9780170355391

More Books

Students also viewed these Accounting questions