Merlot Company has determined its activity cost pools and cost drivers to be the following: Cost pools Setup $56,000 Material handling 12,800 Machine operation 240,000
Merlot Company has determined its activity cost pools and cost drivers to be the following:
Cost pools |
|
|
Setup |
| $56,000 |
Material handling |
| 12,800 |
Machine operation |
| 240,000 |
Packing |
| 60,000 |
Total indirect manufacturing costs |
| $368,800 |
Cost drivers |
|
|
Setups |
| 400 |
Material moves |
| 800 |
Machine hours |
| 16,000 |
Packing orders |
| 1,000 |
One product made by Merlot, metal casements, used the following activities during the period to produce 500 units:
Setups |
| 20 |
Material moves |
| 80 |
Machine hours |
| 1,900 |
Packing orders |
| 150 |
Required
a. Calculate the cost per unit of activity for each activity cost pool for Merlot Company.
b. Calculate the manufacturing overhead cost per metal casement manufactured
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started