Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

mework i Saved On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C., for $360

image text in transcribed
image text in transcribed
mework i Saved On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C., for $360 million. The expected completion date is April 1. 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 60 180 Costs incurred during the year Estimated costs to complete as of December 31 2022 $120 70 2023 $70 Required: 1. Compute the revenue and gross profit will Sanderson report in its 2021 2022 and 2023 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2021 2022, and 2023 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2022 are $140 million instead of $70 million, Compute the amount of revenue and gross profit or loss to be recognized in 2022 assuming Sanderson recognizes revenue over time according to percentage of completion. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Compute the revenue and gross profit will Sanderson report in its 2021, 2022, and 2023 Income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. (Enter your answers in millions. Loss amounts should be indicated with a minus sign. Use percentages as calculated and rounded in the table below to arrive at your final answer.) Percentages of completion Choose numerator Choose denominator Actual costs to date Estimated total costs = % complete to date - = 2023 2021 To date Recognized in prior years Recognized in 2021 0 Construction revenue Continens Percentages of completion Choose numerator El Choose denominator Actual costs to date Estimated total costs % complete to date Ta 202 202 2021 R ecognized in prior years To date Recognized in 2021 Construction revenue Construction expense Gross profit (loss) 2022 Recognized in prior years To date Recognized in 2022 Construction revenue Construction expense Gross profit (loss) 2023 Recognized in prior years To date Recognized in 2023 Construction revenue Construction expense Gross profit (loss) Required 2 >

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

6. Explain the power of labels.

Answered: 1 week ago

Question

10. Discuss the complexities of language policies.

Answered: 1 week ago