Michael Kors prepares a production budget for the next three months: 5,600 units in July, 7,800 units in August, and 8,300 units in September Production
Michael Kors prepares a production budget for the next three months: 5,600 units in July, 7,800 units in August, and 8,300 units in September Production requires both skilled tabor and unskilled tabor, specifically each unit requires 2.2 hours of skilled labor (paid $22 per hour and 16 hours of unskilled labor (paid $15 per hour). How much direct labor costs will Michael Kors budget in August? Multiple Choice $377,520 $564720 $79.400 5036.00