Mickey Maris, the project manager of the Equipment Upgrade project and his team are discussing the Monitor Communications process. Mickey points out that in order
Mickey Maris, the project manager of the Equipment Upgrade project and his team are discussing the Monitor Communications process. Mickey points out that in order to ensure that we are communicating relevant and correct information to our stakeholders, we need to make changes to the reporting when we find that the reports are either incorrect or not containing relevant information. Which process output ensures that this happens