Question

1 Approved Answer

Mini Project Case Willmontt s is a small OKC general contractor with 5 - 1 5 employees depending on how busy they get. The company

Mini Project Case
Willmontts is a small OKC general contractor with 5-15 employees depending on how busy they
get. The company has engaged in a number of construction projects which has required them to
preform a wide range of routine to innovative business practices. They have decided to diversify
their revenue and look for a new field to move in and expand their business within OKC metroplex
area. Therefore, they already performed feasibility study to assess the possibility of expanding
into other fields such as providing plumbing services or heat and air services, electrical
services or property management. After receiving the completed feasibility study,
Willmonts have chosen the field that they want to move on. At this point they have to define
a marketing strategy.
The Operations officer and the business co-owner (George Cranston) of Willmotts has discussed
this subject with Henry Willmont, the companys CEO and they have decided to employ a
consulting company to
1- design a marketing study project
2- manage the marketing study project
Mr. Cranston has made an agreement with your team as the consulting company to achieve those
three goals. Willmonts will customize its systems, practices and business processes to conform to
project requirements defined by you. Team leader will be the CEO of the consulting company and
lead this project. Team expects to 1-manage the project which is mainly done through mini projects.
Generally, from the Willmonts perspective, the project will likely need to accomplish the
following (all information should be collected for OK and OKC unless it is mentioned otherwise):
1. Market outlook for OKC
a. Available market segments
b. List of top ten competitors
c. Market size in terms of dollar value
d. Demographic study of customers
2. Develop a marketing strategy to penetrate the requested market in OKC
3. Communication strategy
a. Advertising strategies currently being used by the companies in the field and the
problems that you can identify with current advertising strategies in the field.
b. Suggest a promotional slogans/mottos that communicate the major benefits of the
business
c. Suggest medium of advertisement and provide an estimation of the cost
d. Suggest an advertising strategy to penetrate the market
4. Managing the firms physical evidence
a. Your team suggestion over a truck wrapping.
b. Develop strategies that enhance the firms touch and taste appeal
Willmonts is considering to offer their services in the following cities.
i. North of Oklahoma City
1. Edmond
2. Guthrie
3. Nichols Hills
4. village
ii. East of Oklahoma City
1. Del City
2. Midwest City
iii. South of Oklahoma City
1. Valley Brook
2. Moore
3. Norma
iv. West of Oklahoma City
1. Mustang
2. Yukon and El Reno
3. Minco and Union City
Willmonts has allocated a maximum of $20,000 for this market study project. Each team member
is paid 40 USD per hour. Use this numbers to calculate the maximum hours of work that you will
be paid to work on it. This hours should cover both managing the project and doing the marketing
study. You have been asked to ensure that your project does not go over this figure, and, if possible,
that the total project cost is under that amount. Willmonts and consulting company (your team)
agreed that they would like to have the market study project by the due date.
After reading the scenario, please consider the following points for miniproject one:
1. As a consulting company, you have agreed to
a. Define a project to study the market and manage the project
b. Perform the market study
c. Present the result in a report format
2. In this project, you should define the project using the concepts you
have learned in different book chapters.
3. You must add the project management, communication, testing, and
training tasks as needed to make the project successful. Use the
information in the case, other assignments, and your ideas to ensure a
quality implementation throughout the project.
Mini-Project 1 Task List
1. Please develop an effective charter.
a. An effective charter should authorize the project manager to proceed.
It should also help the project manager, core team, and sponsor
develop a shared understanding. It should further help the project
manager, core team, and sponsor commit to the project.
b. A Charter is like a contract because
i. it is an agreement entered into by the two parties through
consensus, and one of them cannot arbitrarily change it.
ii. It is a living document that can be changed if both parties agree
and both receive something of value.
c. In the meantime, a charter is different from a contract since
i. parties agree to the project's " spirit. " The details are not
worked out yet, so there is no "fine print" as in many contracts.
ii. The schedule, budget, exact deliverables, etc., may change, but
all parties agree to keep working hard to help make the project
successful.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Risk Management

Authors: Genserik Meyer, Thierry, Reniers

3rd Edition

311066531X, 978-3110665314

More Books

Students also viewed these General Management questions