MNO Company began construction of a new facility and took out s $2,000,000, 6% construction loan on April 1, 2020. MNO made payments to the
MNO Company began construction of a new facility and took out s $2,000,000, 6% construction loan on April 1, 2020. MNO made payments to the general contractor of $400,000 on April 1, $900,000 on August 31 and $500,000 on December 3!
Required: Compute the amount of interest that Agasse would capitalize in 2020. Show all your work.