AZ Devices manufactures a number of different electronic devices. One of their products is AZ calculator. Calculators are sold every day of the month, but are only produced at the factory days per week, Monday through Friday.
Their monthly demand for these calculators is The factory is open hours per day. Assume an average of working days per month in the factory. You will be using daily demand, so use this information to calculate the daily demand.
LINE BALANCING PRECEDENCE DIAGRAM
Remember, the factory is open days per month. The assembly line runs hours per day. The following precedence diagram gives the necessary data to answer the line balancing related questions that follow.
LINE BALANCING PROBLEMS
Question #Make sure this answer is correct before moving on What is the CYCLE TIME that ensures the desired output rate?
NOTE: NEVER ROUNDUP YOUR CYCLE TIME!!! You should be able to figure out why this should never be done. Think about it
Question #
What is the theoretical minimum number of workstations?
ALWAYS ROUND UP workstations. Again, you should know why,
As you know, you should always round up your theoretical minimum number of workstations. Nonetheless, be aware that the calculated theoretical minimum number
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started