Module 4 Exam, Part II 1) The following data is received from your contractor on a key component of the project: Budgeted Cost of Work

image text in transcribed
image text in transcribed
Module 4 Exam, Part II 1) The following data is received from your contractor on a key component of the project: Budgeted Cost of Work Performed (BCWP) = $300 Budgeted Cost of Work Scheduled (BCWS) = $200 Actual Cost of Work Performed (ACWP) = $500 Which of the following Earned Value Management (EVM) metrics can be determined from these data? O CV = - $200 and SV = $100 O % Spent = 66% and % Complete = 50% O CPI = 1.67 and SPI = 0.67 O Cost Variance (CV) = $200 and Schedule Variance (SV) = - $100

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Cost Accounting

Authors: William N. Lanen, Shannon Anderson, Michael W Maher

6th edition

1259969479, 1259565408, 978-1259969478

More Books

Students also viewed these Accounting questions

Question

2. What types of information are we collecting?

Answered: 1 week ago

Question

5. How quickly can we manage to collect the information?

Answered: 1 week ago

Question

3. Tactical/strategic information.

Answered: 1 week ago