Module 6 Case Study Controlling Project Risks Student Name:________________ Date:________________________ Now the project is well underway, with several challenges being properly addressed.You just received an
Module 6 Case Study
Controlling Project Risks
Student Name:________________
Date:________________________
Now the project is well underway, with several challenges being properly addressed.You just received an email message from the electrical contractor outlining a 3-week delay in the Install and Terminate Electrical Devices activity, due to defective material.
The electrical contractor's SOW states that if there is a potential delay, all subcontractors must inform you in writing within 48 hours of the onset of the delay, and the email message meets this requirement.
The project has already been significantly delayed due to severe weather conditions. Although your risk analysis included a schedule contingency for weather conditions and the receipt of defective materials, this is a serious problem that threatens to further delay the project.
- The contractor suggests that it may ultimately be more cost-effective to buy materials from another contractor, although the initial cost of materials will be higher. What are the considerations for changing contractors?
Answer:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started