Money that the firm has already spent or is committed to spend regardless of whether a project is taken is called a(n) sunk cost. opportunity
Money that the firm has already spent or is committed to spend regardless of whether a project is taken is called a(n)
sunk cost.
opportunity cost.
erosion cost.
fixed cost.
None of the above.