Monica is the Project Manger of the OPS PROJECT. She has to make a choice when crashing the OPS's schedule. She has to make decision
Monica is the Project Manger of the OPS PROJECT. She has to make a choice when "crashing" the OPS's schedule. She has to make decision to trade-off schedule vs cost as is often the case in most projects. Where should Judth invest her Project dollars? Question 23 options: a) Crash a critical path task with the greatest schedule saving for that dollar b) Crash the longest critical path task. c) Crash a late, risky critical path task d) Crash the first critical path task in the project