Monty Construction Company uses the percentage-of-completion method of accounting. In 2020, Monty began work under contract #E2-D2, which provided for a contract price of $2,187,000.

image text in transcribedimage text in transcribed

Monty Construction Company uses the percentage-of-completion method of accounting. In 2020, Monty began work under contract #E2-D2, which provided for a contract price of $2,187,000. Other details follow:

2020

2021

Costs incurred during the year $658,560 $1,408,000
Estimated costs to complete, as of December 31 909,440 0
Billings during the year 421,000 2,187,000
Collections during the year 348,000 1,527,000
What portion of the total contract price would be recognized as revenue in 2020? In 2021?
Revenue recognized in 2020 $

Revenue recognized in 2021 $

SHOW LIST OF ACCOUNTS

LINK TO TEXT

Assuming the same facts as those above except that Monty uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in 2021?
Revenue recognized in 2021 $

SHOW LIST OF ACCOUNTS

LINK TO TEXT

Prepare a complete set of journal entries for 2020 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

(To record cost of of construction.)

(To record progress billings.)

(To record collections.)

(To recognize revenue.)

Question 9 Monty Construction Company uses the percentage-of-completion method of accounting. In 2020, Monty began work under contract #E2-D2, which provided for a contract price of $2,187,000. Other details follow: Costs incurred during the year Estimated costs to complete, as of December 31 Billings during the year Collections during the year 2020 2021 $658,560 $1,408,000 909,440 -0- 421,000 2,187,000 348,000 1,527,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 Revenue recognized in 2021 s SHOW LIST OF ACCOUNTS LINK TO TEXT Assuming the same facts as those above except that Monty uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue 20217 Revenue recognized in 2021 SHOW LIST OF ACCOUNTS LINK TO TEXT Prepare a complete set of journal entries for 2020 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter o for the amounts. For costs incurred use account Materials, Cash, Payables.) Account Titles and Explanation Debit Credit (To record cost of of construction.) (To record progress billings.) (To record collections.) (To recognize revenue.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

2 Principles Of Financial And Managerial Accounting

Authors: Pollard, Sherry T. Mills, Walter T. Harrison Jr.

0136009891, 978-0136009894

More Books

Students also viewed these Accounting questions

Question

solve

Answered: 1 week ago

Question

What is electric dipole explain with example

Answered: 1 week ago

Question

What is polarization? Describe it with examples.

Answered: 1 week ago