Question

1 Approved Answer

Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made

Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:

Machine-hours required to support estimated production155,000Fixed manufacturing overhead cost$654,000Variable manufacturing overhead cost per machine-hour$4.20

Required:

1. Compute the plantwide predetermined overhead rate.

2. During the year, Job 400 was started and completed. The following information was available with respect to this job:

Direct materials$350Direct labor cost$240Machine-hours used37

Compute the total manufacturing cost assigned to Job 400.

3. If Job 400 includes 60 units, what is the unit product cost for this job?

4. If Moody uses a markup percentage of 120% of its total manufacturing cost, then what selling price per unit would it have established for Job 400?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting A Practical Approach

Authors: Jeffrey Slater, Debra Good

13th Canadian edition

134616316, 134166698, 9780134632407 , 978-0134166698

More Books

Students also viewed these Accounting questions

Question

2. Information that comes most readily to mind (availability).

Answered: 1 week ago

Question

3. An initial value (anchoring).

Answered: 1 week ago