Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine hours. At the beginning of the year, the company made the following estimates: Machine-hour's required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 155,600 $ 655,000 $ 4.50 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor cost Machine-hours used $ 320 $ 250 38 Compute the total manufacturing cost assigned to Job 400. 3. If Job 400 includes 60 units, what is the unit product cost for this job? 4. If Moody uses a markup percentage of 110% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? Answer is not complete Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the plantwide predetermined overhead rate (Round your answer to 2 decimal places) Predetermined overhead rate 8.73 por MH Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Compute the total manufacturing cost assigned to Job 400. (Round your intermediate calculations to 2 decimal places and your final answer to the nearest dollar amount.) Total manufacturing cost 332 Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 IF Job 400 includes 60 units, what is the unit product cost for this job? (Round your answer to the nearest whole dollar.) Unit product cost 902 Required 1 Required 2 Required 3 Required 4 If Moody uses a markup percentage of 110% of its total manufacturing cost, then what selling price per unit would it have established for Job 400? (Round your answer to the nearest whole dollar.) Selling price per unit