Moon Manufacturing budgeted fixed overhead costs of $2.50 per unit at an anticipated production level of 1,450 units. In July the company incurred actual
Moon Manufacturing budgeted fixed overhead costs of $2.50 per unit at an anticipated production level of 1,450 units. In July the company incurred actual fixed overhead costs of $5,000 and actually produced 1,200 units. What is Moon's fixed overhead budget variance for July?