Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer into the fall. The summer months are busy for the realty company, and it believes it can sell the houses almost as soon as they are readysometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside realtors that it is insisting a project management network accompany the contractor's bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this time frame, the realtor wants to be able to charge the contractor a penalty. The MHC is concerned about the prospect of a penalty. They want to be confident they can meet the house's deadline before entering into any agreement with a penalty involved.

Moore has experienced house builders, so it was not difficult for them to list the activities involved in building a house or estimate activity times. However, they made their estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. The table below shows a list of the activities for building a house and the activity time estimate.

  1. Use the Normal time given in the table below to reduce the project by 6 days. What is the added cost? Show the activity/activities to crash for each day, i.e., what activity should be crashed on the 1st day, what activity should be crashed on the day, 2nd etc. image text in transcribed
Time (days) Activity Description Predecessor Crash time Normal cost Normal time 4 Crash cost a none 6 20 b a 3 5 28 Excavation, pour footers Lay foundation Frame and roof Sewer (floor) drains Install insulation b 4 5 22 e b 2 3 25 f 4 5 30 Pour basement floor e 3 5 18 f 3 4 22 i J f 2 3 20 5 8 23 k 1 6 8 28 $10 $22 $15 $21 $25 $12 $20 $20 $11 $16 $18 $23 $25 $12 $17 $20 $18 $15 $25 ick | m 8 10 26 n 3 4 29 Install windows Rough electrical wiring Install furnace Exterior brickwork Install plasterboard Roof shingles Attach gutter Grading Lay subflooring Lay driveway Kitchen, sink, appliances Painting Finish wood floor O 2 5 31 3 16 7 5 q * - s o E 2o - > 4 22 r 6 8 30 t 4 8 28 V 6 8 24 W 5 8 34

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Continuous Auditing A Complete Guide

Authors: Gerardus Blokdyk

2019th Edition

0655540318, 978-0655540311

More Books

Students also viewed these Accounting questions