More Info Overall Process Attributes Average demand: 2 , 7 0 0 / week ( 1 , 4 0 0 L ; 1
More Info
Overall Process
Attributes
Average demand: week L; S
Batch size:
Number of shifts per day:
Availability: hours per shift with two minute lunch breaks
Process Step
Press
Cycle time seconds
Setup time hours
Uptime
Operators
Every Part Every week
WIP day of sheets before Press
Process Step
Pierce & Form
Cycle time seconds
Setup time minutes
Uptime
Operators
WIP LSbefore Pierce & Form
Process Step
Finish Grind
Cycle time seconds
Setup time minutes
Uptime
Operators
WIP LSbefore Finish Grind
Process Step
Shipping
WIP LSafter Finish Grind
Supplier
One shipment a day in trays of pieces
Information
Information Flow
All communications from customer are electronic:
day Forecasts
Daily Order
All communications to supplier are electronic
week Forecast
Weekly Fax
There is a weekly schedule manually delivered to Press, Pierce & Form, and Finish Grind and a Daily Ship Schedule manually delivered to Shipping
All material is pushedtable below provides the parameters for a new current state value stream map for the family of retainers at the Jensen Bearings Inc. firm
described in the chapter. This table depicts the value stream after Kline Steel agrees to accept daily orders for steel sheets and also agrees to deliver
on a daily basis. Calculate each component of the new value stream's reduced lead time. Jensen Bearings operates days per week.
Click the icon to view the data from the new current state value stream map at Jensen Bearings Inc.
a How many days of raw material does the Bearing's plant now hold?
The plant holds
days of raw material. Enter your response rounded to one decimal place.
b How many days of work in process inventory is held between Press and Pierce & Form?
The inventory is held
days. Enter your response rounded to one decimal place.
c How many days of work in process inventory is held between Pierce & Form and Finish Grind?
The inventory is held
days. Enter your response rounded to one decimal place.
d How many days of work in process inventory is held between Finish Grind and Shipping?
The inventory is held
days. Enter your response rounded to one decimal place.
e What is the new value stream's production lead time?
The production lead time is
days. Enter your response rounded to one decimal place.
f What is the new value stream's processing time?
The processing time is
seconds. Enter your response as a whole number.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started