Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Most of this question is already answered, I just need help on the questions I left blank. I have included screenshots of the questions as

Most of this question is already answered, I just need help on the questions I left blank. I have included screenshots of the questions as well as the excel work sheet that was provided with some of the work I've done. Thank you!

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed

Excel Activity: Capital Budgeting Tools Question 1 7.14/10 Excel Activity: Capital Budgeting Tools Submit Start with the partial model in the file Ch12 P25 Build a Model.xlsx. Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Year 0 Expected Net Cash Flows Project A Project B -$365 -$565 -330 180 -220 180 1 2 3 -110 180 4 180 660 660 5 180 6 180 958 -220 7 180 The data has been collected in the Microsoft Excel file below. Download the spreadsheet and perform the required analysis to answer the questions below. Do not round intermediate calculations. x Download spreadsheet Ch12 P25 Build a Model-8ee6c2.xlsx a. If each project's cost of capital is 11%, which project should be selected? Round your answers to the nearest cent. NPV (Project A): $ 311.38 g NPV (Project B): $ 283.20 Project A should be selected. If the cost of capital is 17%, what project is the proper choice? Round your answers to the nearest cent. NPV (Project A): $ 76.96 a. If each project's cost of capital is 11%, which project should be selected? Round your answers to the nearest cent. NPV (Project A): $ 311.38 NPV (Project B): $ 283.20 Project Ay should be selected. If the cost of capital is 17%, what project is the proper choice? Round your answers to the nearest cent. NPV (Project A): $ 76.96 NPV (Project B): $ 141.03 Project By should be selected. b. Construct NPV profiles for Projects A and B. Choose the correct graph. A. B. NPV Profiles NPV Profiles $1,200 $1,200 $1,000 $1,000 $800 $800 $600 $600 $400 5400 $200 $200 SO 0% -$200+ 5% 10% 15% 20% 30% SO 0% -$200 5 10% 15% 20% 25% 30% D. NPV Profiles NPV Profiles $1,200 $1,200 $1,000 $1,000 $800 $800+ $600 $600 5400 5400 $200 $200+ SO 0% -$200 5% 10% 15% 20% 25% 30% SO 0% -$200 5% 10% 15% 250 20% 30% -$400 Cost of Capital - Project A -Project B -$4001 Cost of Capital Project A -Project B The correct graph is graph Dva c. What is each project's IRR? (Hint: Using the Excel IRR function, set the guess parameter to be 10%.) Round your answers to two decimal places. IRR (Project A): 19.52 % IRR (Project B): 25.28 % d. What is the crossover rate, and what is its significance? (Hint: Using the Excel IRR function, set the guess parameter to be 10%.) Round your answer for the crossover rate to two decimal places and for the NPV to the nearest cent. The crossover rate is 12.58 %. The crossover rate represents the cost of capital at which the two projects have the NPV of $ 241.59 IRR (Project B): 25.28 % d. What is the crossover rate, and what is its significance? (Hint: Using the Excel IRR function, set the guess parameter to be 10%.) Round your answer for the crossover rate to two decimal places and for the NPV to the nearest cent. The crossover rate is 12.58 %. The crossover rate represents the cost of capital at which the two projects have the NPV of $ 241.59 e. What is each project's MIRR at a cost of capital of 11%? At r = 17%? Round your answers to two decimal places. Project A 15.28 % MIRR at r = 11% Project B 17.63% 20.78 %% MIRR at r = 17% 18.31 % f. What is the regular payback period for these two projects? Round your answers to two decimal places. Regular payback period (Project A): years Regular payback period (Project B): years g. At a cost of capital of 11%, what is the discounted payback period for these two projects? Round your answers to two decimal places. Discounted payback period (Project A): years Discounted payback period (Project B): years h. What is the profitability index for each project if the cost of capital is 11%? Round your answers to three decimal places. Profitability index (Project A): Profitability index (Project B): Check My Work Reset Problem $660 1 Capital Budgeting Tools 2 3 Expected Net Cash Flows 4 Time Project A Project B 5 0 -$365 $565 1 -$330 $180 7 2 -$220 $180 3 3 $110 $180 2 4 $180 0 5 $660 $180 1 6 $958 $180 2 7 $220 $180 3 4 a. Finding each project's NPV at two different costs of capital 5 WACC 11% 6 WACC2 17% 7 Project A Project B 8 NPV at WACC1 $311.38 $283.20 9 NPV at WACC2 $76.96 $141.03 CO 1 b. Constructing NPV profiles for Projects A and B -2 NPV Cost of capital -3 Project A Project B -4 B15 $311.38 $283.20 -5 0% $1.033.00 $695.00 -6 2% $863.03 $599.96 7 4% $713.08 $515.37 -8 6% $580.53 $439.83 -9 8% $463.15 $372.15 0 10% $359.01 $311.32 -1 12% $266.46 $256.48 Sheet1 Formulas Project A =NPV(11%,B6:B12)+B5 =NPV(17%,B6:B12)+B5 Project B =NPV(11%, C6:C12)+C5 =NPV(17%,C6:C12)+C5 Project A $311.38 =$B$5+NPV(A25 $B$6:$B$12) =$B$5+NPV(A26 $B$6:$B$12) =$B$5+NPV(A27,$B$6:$B$12) =$B$5+NPV(A28,$B$6:$B$12) =$B$5+NPV(A29,$B$6:$B$12) =$B$5+NPV(A30,$B$6:$B$12) =$B$5+NPV(A31,$B$6:$B$12) NPV Project B $283.20 =$C$5+NPV(A25 $C$6:$C$12) =$C$5+NPV(A26,$C$6:$C$12) =$C$5+NPV(A27,$C$6:$C$12) =$C$5+NPV(A28,$C$6:$C$12) =$C$5+NPV(A29,$C$6:$C$12) =$C$5+NPV(A30, $C$6:$C$12) =$C$5+NPV(A31, $C$6:$C$12) b. Constructing NPV profiles for Projects A and B NPV Cost of capital Project A Project B B15 $311.38 $283.20 0% $1.033.00 $695.00 2% $863.03 $599.96 4% $713.08 $515.37 6% $580.53 $439.83 8% $463.15 $372.15 10% $359.01 $311.32 12% $266.46 $256.48 14% $184.08 $206.89 16% $110.66 $161.94 18% $45.11 $121.07 20% -$13.47 $83.83 22% -$65.91 $49.79 24% -$112.88 $18.62 26% -$155.02 -$10.00 28% -$192.84 -$36.34 30% -$226.84 -$60.62 Project A $311.38 =$B$5+NPV(A25 $B$6:$B$12) =$B$5+NPV(A26,$B$6:$B$12) =$B$5+NPV(A27,$B$6:$B$12) =$B$5+NPV(A28,$B$6:$B$12) =$B$5+NPV(A29,$B$6:$B$12) =$B$5+NPV(A30,$B$6:$B$12) =$B$5+NPV(A31,$B$6:$B$12) =$B$5+NPV(A32,$B$6:$B$12) =$B$5+NPV(A33,$B$6:$B$12) =$B$5+NPV(A34, $B$6:$B$12) =$B$5+NPV(A35,$B$6:$B$12) =$B$5+NPV(A36,$B$6:$B$12) =$B$5+NPV(A37,$B$6:$B$12) =$B$5+NPV(A38, $B$6:$B$12) =$B$5+NPV(A39,$B$6:$B$12) =$B$5+NPV(A40,$B$6:$B$12) NPV Project B $283.20 =$C$5+NPV(A25, $C$6:$C$12) =$C$5+NPV(A26,$C$6:$C$12) =$C$5+NPV(A27 $C$6:$C$12) =$C$5+NPV(A28,$C$6:$C$12) =$C$5+NPV(A29, $C$6:$C$12) =$C$5+NPV(A30, $C$6:$C$12) =$C$5+NPV(A31,$C$6:$C$12) =$C$5+NPV(A32, $C$6:$C$12) =$C$5+NPV(A33,$C$6:$C$12) =$C$5+NPV(A34, $C$6:$C$12) =$C$5+NPV(A35,$C$6:$C$12) =$C$5+NPV(A36,$C$6:$C$12) =$C$5+NPV(A37,$C$6:$C$12) =$C$5+NPV(A38,$C$6:$C$12) =$C$5+NPV(A39,$C$6:$C$12) =$C$5+NPV(A40,$C$6:$C$12) Chart Title $1,200.00 $1,000.00 $800.00 $600.00 $400.00 30% -$226.84 -$60.62 =$B$5+NPV(A40,$B$6:$B$12) =$C$5+NPV(A40, $C$6:$C$12) Chart Title $1,200.00 $1,000.00 $800.00 $600.00 $400.00 $200.00 $0.00 0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% 22% 240 26% 28% 30% -$200.00 -$400.00 Series1 Series2 c. Finding each project's IRR (Using the Excel IRR function, set the guess parameter to be 10%.) Project A Project B Project A IRR 19.52% 25.28% =IRR(B5:B12) Project B =IRR(C5:C12) d. Finding the crossover rate (Using the Excel IRR function, set the guess parameter to be 10%.) Project ACF = Year CFA- CFB 0 $200 =B5-C5 IRR 19.52% 25.28% =IRR(B5:B12) =IRR(C5:C12) d. Finding the crossover rate (Using the Excel IRR function, set the guess parameter to be 10%.) Project ACF = Year CFA - CFB 0 $200 =B5-C5 1 -$510 =B6-C6 2 -$400 =B7-C7 3 -$290 =B8-C8 4 $480 =B9-C9 5 $480 =B10-C10 6 $778 =B11-C11 7 -$400 =B12-C12 Crossover rate NPV of Project A at the crossover rate NPV of Project B at the crossover rate 12.58% $241.59 $241.59 =IRR(B70:B77) =NPV(B79,B6:B12)+B5 =NPV(B79, C6:C12)+C5 e. Finding each project's MIRR at two different costs of capital WACC1 11% WACCZ 17% Project A Project B MIRR at WACC1 15.28% 17.63% MIRR at WACC2 18.31% 20.78% Project A =MIRR(B5:B12, 11%, B84) =MIRR(B5:B12,385,385) Project B =MIRR(C5:C12, B84,B84) =MIRR(C5:C12,885,885) f. Finding the regular payback period for these two projects Project A Cumulative cash flow Intermediate calculation for payback Year 0 Intermediate calculation for payback Cumulative cash flow #N/A Cash flow -$365.00 f. Finding the regular payback period for these two projects Project A Cumulative cash flow Intermediate calculation for payback Intermediate calculation for payback Year 0 1 2 3 4 5 6 Cash flow -$365.00 -$330.00 -$220.00 $110.00 $660.00 $660.00 $958.00 -$220.00 Cumulative cash flow #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A 7 Regular payback period (years) #N/A Project B Cumulative cash flow Intermediate calculation for payback Intermediate calculation for payback Year 0 1 2 Cumulative cash flow #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A Cash flow -$565.00 $180.00 $180.00 $180.00 $180.00 $180.00 $180.00 $180.00 3 4 #N/A #N/A #N/A #N/A #N/A #N/A #N/A 5 6 7 Regular payback period (years) #N/A a Finding the discounted navback neriod for these two proiects 11% 8 WACC 9 Project A Discounted cash flow Cumulative discounted cash flow Intermediate calculation for payback Discounted cash flow Interme 0 Year 1 0 2 1 3 2 4 3 5 4 6 5 7 6 8 7 9 o Discounted payback period (years) 1 2 Project B Cash flow -$365.00 -$330.00 -$220.00 $110.00 $660.00 $660.00 $958.00 -$220.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A Cumulative discounted cash flow #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A Discounted cash flow Cumulative discounted cash flow Intermediate calculation for payback Discounted cash flow Interme 3 Year 4 0 5 1 6 2 7 3 8 4 9 5 0 6 1 7 2 3 Discounted payback period (years) 4 Cash flow -$565.00 $180.00 $180.00 $180.00 $180.00 $180.00 $180.00 $180.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A Cumulative discounted cash flow #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A h. Finding the profitability index for each project WACC 11% Project A PV of future cash flows Profitability index Project B Project A Project B #N/A #N/A #N/A #N/A

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Financial Analytics The Path To Investment Profits

Authors: Edward E Williams, John A Dobelman

1st Edition

9813224258, 978-9813224254

Students also viewed these Finance questions