MPS The forecast for each period is 70 units. The starting inventory is zero. The MPS rule is to schedule production if the projected
MPS The forecast for each period is 70 units. The starting inventory is zero. The MPS rule is to schedule production if the projected inventory on hand is negative. The production lot size is 100 units. The following table shows committed orders. Period Customer Orders 1 80 2 50 3 30 4 10