MSI's current data center is located on the U.S. Gulf Coast, which is often plagued with catastrophic weather events. The company desires to implement a

MSI's current data center is located on the U.S. Gulf Coast, which is often plagued with catastrophic weather events. The company desires to implement a new state-of-the-art data center for its North American operations, capable of supporting strategic growth and expansion in an area with more stable weather patterns. The Chief Information Officer (CIO) for MSI, Ms. Stephanie Jones, has been selected to lead this project. The Chief Executive Officer (CEO), Mr. Gerald O'Conner, would like to see the project completed within 18 months. The start date will be the first of next month. The company has allocated $6 million in funding and identified an 8,000 square foot facility in a weather-safe location

The project objectives are Build-out a new state-of-the-art 8,000 square foot facility. o Ensure power; heating, ventilation, and air conditioning (HVAC); and communication resources are sufficient to support the new data center. Relocate 225 physical and virtual servers along with the supporting network infrastructure to the new data center. Establish a help-desk operation for the new data center (Tier 1 and Tier 2). Perform improvements on the existing office space, and relocate 70 IT employees from the old data center to their new office space. Ensure business applications are migrated from the old data center to the new and tested for proper functionality. Ensure data security concerns (physical, logical, and personnel) are addressed.

(Provide a brief introduction to the MSI expansion and relocation project.)

  1. Purpose ofProject Management Plan

2. (Provide the purpose of the project charter [mission statement].)

The intended audience of the MSI Relocation and expansion projectPMP is all project stakeholders, including the project sponsor, senior leadership and the project team.

Provide an executive summary of project charter(MSI Project).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions

Question

Differentiate between a push and pull production system.

Answered: 1 week ago