MSK Construction Company contracted to construct a factory building for $ 5 2 5 , 0 0 0 . Construction started during 2 0 X

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows:
20X120X2
Costs incurred during the year $ 290,000 $ 150,000
Estimated additional cost to complete 145,000
Billings during the year 260,000265,000
Cash collections during the year 240,000285,000
Required:
Record the preceding transactions in MSKs books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.
Record the preceding transactions in MSKs books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Detecting Accounting Fraud Before Its Too Late

Authors: Oriol Amat

1st Edition

1119566843, 9781119566847

More Books

Students also viewed these Accounting questions

Question

Consider some type of redress for the customer, such as a coupon.

Answered: 1 week ago

Question

Demonstrate through language that you are grateful to be informed.

Answered: 1 week ago

Question

Always mention the specifi c problem the customer faced.

Answered: 1 week ago