Multiple Choice Question 74 On May 1, 2017, Vaughn Manufacturing began construction of a building. Expenditures of $620400 were incurred monthly for 5 months beginning
Multiple Choice Question 74 On May 1, 2017, Vaughn Manufacturing began construction of a building. Expenditures of $620400 were incurred monthly for 5 months beginning on May 1. The building was completed and ready for occupancy on September 1, 2017. For the purpose of determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures orn the building during 2017 were O $2481600 3102000. $517000 O $620400