Question
Multiple Choice Select the best response for the following statements. If you assign a resource to a task with more units than the resource has
Multiple Choice
Select the best response for the following statements.
If you assign a resource to a task with more units than the resource has available, then the resource is considered to be which of the following?
maximized
over utilized
compromised
over allocated
Which of the following lets you choose the scheduling option you need?
Actions tag list
work formula
Assign Resources dialog box
effortdriven scheduler
A task plus a resource equals which of the following?
work
an assignment
over allocation
duration
If, on an effortdriven task, after an initial assignment, you assign more resources to a task, which of the following happens to the task's duration?
It doubles.
It decreases.
It is reduced by half.
It increases.
Where do you normally record the dollar value of the cost resources for your project?
on the Resource Sheet in the Cost column
on the Resource Sheet in the Std. Rate column
in the Assign Resources dialog box when the cost resource is assigned
in a separate Excel spreadsheet
The first time you are making resource assignments to a task, and you assign two resources at the same time, each at 100% assignment units, to a task with 24 hours duration, each resource will work on the task for how long?
12 hours
24 hours
36 hours
48 hours
To assign more than one resource to a task using the Assign Resources dialog box, click on the first resource name, then hold down the ______ key while clicking the second resource name, and then click Assign.
Alt
Shift
Ctrl
none of the above
Which of the following is an advantage of assigning resources to tasks?
You can see if the resource assignment affects task duration.
You can track the progress of the resource in working on the task.
You can track resource and task costs.
All of the above are advantages of assigning resources to tasks.
If you assign a(n) _______________ quantity of a material resource to a task, Microsoft Project will adjust the quantity and cost of the resource as the task's duration changes.
variablerate
openended
fixed unit
declining rate
You can assign resources to tasks using all of the following methods, except the _______________.
Assign Resources dialog box
Resource Names column
Resource Sheet
Resource tab on the Task Information dialog box
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started