Multiple Versus Single Overhead Rates, Activity Drivers Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected
Multiple Versus Single Overhead Rates, Activity Drivers
Deoro Company has identified the following overhead activities, costs, and activity drivers for the coming year:
Activity | Expected Cost | Activity Driver | Activity Capacity |
Setting up equipment | $559,590 | Number of setups | 690 |
Ordering costs | 357,200 | Number of orders | 18,800 |
Machine costs | 826,000 | Machine hours | 41,300 |
Receiving | 373,800 | Receiving hours | 8,900 |
Deoro produces two models of dishwashers with the following expected prime costs and activity demands:
Model A | Model B | |
Direct materials | $571,000 | $833,000 |
Direct labor | $465,000 | $492,000 |
Units completed | 15,500 | 8,800 |
Direct labor hours | 6,200 | 2,300 |
Number of setups | 450 | 240 |
Number of orders | 6,300 | 12,500 |
Machine hours | 23,500 | 17,800 |
Receiving hours | 2,600 | 6,300 |
The company's normal activity is 8,500 direct labor hours.
Required:
1. Determine the unit cost for each model using direct labor hours to apply overhead. Round intermediate calculations and final answers to nearest cent.
Unit Cost | |
Model A | $ |
Model B | $ |
2. Determine the unit cost for each model using the four activity drivers. Round your answers to nearest cent.
Unit Cost | |
Model A | $ |
Model B | $ |
3. Which method produces the more accurate cost assignment?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started