Muronga Ltd supplied the following details regarding a contract that was still in progress at the end of the accounting period ended 29 February 2019:

Muronga Ltd supplied the following details regarding a contract that was still in progress at the end of the accounting period ended 29 February 2019:

Contract price

N$100 000

Cost to date

N$60 000

Estimated costs to completion

N$12 000

Sales value of work certified

N$75 000

Cost of certified work

N$50 000

Retention amount

N$7 500

Required:

Mark

Calculate the amount of profit on this contract that may be transferred to the profit and loss account for the past accounting period, using each of the following methods:

The work certified method 

The percentage of completion method

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the amount of profit on the contract that may be transferred to the profit and loss acc... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing

Authors: Alan Millichamp, John Taylor

10th Edition

1408044080, 978-1408044087

More Books

Students also viewed these Accounting questions