Muronga Ltd supplied the following details regarding a contract that was still in progress at the end of the accounting period ended 29 February 2019:
Muronga Ltd supplied the following details regarding a contract that was still in progress at the end of the accounting period ended 29 February 2019:
Contract price
N$100 000
Cost to date
N$60 000
Estimated costs to completion
N$12 000
Sales value of work certified
N$75 000
Cost of certified work
N$50 000
Retention amount
N$7 500
Required:
Mark
Calculate the amount of profit on this contract that may be transferred to the profit and loss account for the past accounting period, using each of the following methods:
The work certified methodÂ
The percentage of completion method
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the amount of profit on the contract that may be transferred to the profit and loss acc...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started