MusikFest 1 A Project Management Decision - Making Game Around the world or around the block, Everywhere I go , the kids wanna rock 2
MusikFest
A Project Management DecisionMaking Game
Around the world or around the block,
Everywhere I go the kids wanna rock
Your company, Planners R Us specializes in effectively managing projects. Previous experience has involved conference management systems, commercial construction, and software development projects.
A new, intriguing project offers another opportunity to apply your project management expertise. The university you just graduated from wishes to put together a music festival, MusikFest This will feature a number of top music groups, and should attract interest from students, local residents, and music fans throughout the region.
Your company has met with University officials to develop a list of activities required to make Musikfest a reality. The list on Page includes twelve activities as well as their durations and immediate predecessors. The project plan is also described visually on page with a network diagram. The subscripts on each activity denote the number of weeks of work that activity is expected to require. Arrows denote the order of activities. For instance, activity E cannot be started until activity A is completed, and activity H cannot be started until both C and D are complete. The start and end nodes are dummy nodes and do not need to be worked on Note that at the beginning of the project, activities A C and D are available to start working on as they have no predecessor activities. Be sure to understand the diagram before reading further.
Your job is to allocate workers to tasks each week during the project. Planners R Us has agreed to complete the project in weeks finishing two weeks before the Festival and wants to minimize the costs associated with the project. All tasks AL must be completed in weeks. You have four workers, although you do not need to use all of them every week there are other tasks they can do in your company.
For bookkeeping purposes, your company will charge $ per week for each worker that you use. If you happen to need an additional worker, there is one available, but that person would then not get their other work done; thus, you will be charged $ per week instead of $ for the additional worker. In addition, if the project is late there will be complications during the last two weeks before the Festival, costing Planners R Us $ per week due to a serious loss of goodwill and plenty of negative publicity.
The final cost to consider involves expediting tasks. You can assign an extra worker to a task in any given week in order to finish it in less time. For instance, if a task requires weeks but you assign two workers, it will be completed in one week. However, putting two workers on a task is
The events, activity durations and overall scenario represented in this game are purely fictional. No relationship to an upcoming music concert, real or implied, is suggested.
Bryan Adams, Kids Wanna Rock from the album So Far So Good A & M Records
not quite as efficient as having one worker complete it from start to finish. Doing this requires
additional coordination by you and may require some overtime by the workers. These costs total
an additional $ per week for each task this is done. The most workers that can be assigned to
any task in a week is two since having or more requires so much additional coordination that
no reduction in time is achieved
To summarize, the most workers on any given task is two per week, and the total number of
workers you may employ for any week is at most five You may switch workers between tasks
on any week whether the task is done or not.
Activity Description Duration
weeks
Immediate
predecessors
A Negotiate contract with selected music groups
B Build the stage C
C Find a construction firm
D Screen and hire security personnel
E Complete legal review of signed contract A
F Develop security procedures and coordinate with local police D
G Make arrangements for music group transportation E
H Communicate with agents regarding schedule and layout C D
I Arrange for concession sales F H
J Make sound equipment arrangements E B H
K Process travel visas for international groups G
L Distribute media passes and arrange for MTV recording F
Start
H
G
F
E
D
C
B
A
I
L
K
J
End
Being an experienced manager, you are aware that all projects involve various uncertainties eg
delays, additional requirements, or even improved efficiency that can occur at any time. Since
you do not want to lose your reputation for ontime delivery in Planners R Us you are determined
to plan the project well and be as efficient as possible from the first week on
For now, you want to think about approximately how you will carry out the whole project, but the only decision that needs to be made now is how to allocate workers for the first week. Report this decision t
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started