(Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project
(Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project B Cash Flow $(90,000) 0 0 1 Project A Cash Flow $(90,000) 35,000 35,000 35,000 35,000 35,000 2 3 4 5 0 0 0 230,000 If the appropriate discount rate on these projects is 8 percent, which would be chosen and why? The NPV of Project A is $ (Round to the nearest cent.)