N AN 8 HOUR SHIFT Stage A 20 cars per hour Initial set up time of 20 minute when changing the car model or size
N AN 8 HOUR SHIFT
Stage A 20 cars per hour Initial set up time of 20 minute when changing the car model or size
Stage B 20 cars per hour Must be shut down for maintenance and cleaning for 30 minute after every 90 minute of operation
Stage C 18 cars per hour More customization, but no setups
Where would you place the buffers and what should the buffer capacity in terms of the number of cars? Assume a cost of $5000/unit of storage capacity If you add the buffers, how much does the system capacity increase? How many cars can you now produce per shift?
Reduce setup times
Setup times are always unproductive
Stage A Reduce 20 minute setup 50% reduction, would cost $10,000
Stage B Reduce 30 minute downtime 50% reduction, would cost $20,000
Would you reduce the setup time? If so, at which stages would you reduce setup time and how much would this add to the system capacity? Which is the better option? Why?
What if we can do both? What is the increase to system capacity and at what cost? If you now consider all three options (the first two and the combined option), what is the best solution here?
Part B
Three models, model x, y and Z
Setup is only required for changing the model type of
Stage A Consider an 8 hour shift per day and 6 day per week operation
Determine the batch sequence for the three models that will be processed through the week
Parameters
There's an equal number of batches produced for each model in the week. Therefore the entire weeks output would be equally split across the three models. Within a single day, you would need to produce at least one batch of each model. You could have more than one batch of each model produced within a single day Develop a sequence for how the models will be produced over the 6 day period. Multiple solutions are possible Final complication What happens to Part B analysis if you have a fourth model, Model W in the mix? How would your solution change to incorporate this additional model?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success