Question

1 Approved Answer

n March 1, 2017, Bramble Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The

n March 1, 2017, Bramble Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below:

2017

2018

2019

Contract costs incurred during the year $2,671,200 $2,193,000 $2,395,800
Estimated costs to complete the contract at 12/31 3,688,800 2,395,800 0
Billings to Fabrik during the year 3,170,000 3,510,000 1,650,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Which diagnostic test is most commonly used to confirm PROM?

Answered: 1 week ago

Question

What is the hallmark clinical feature of a molar pregnancy?

Answered: 1 week ago