N4 In computing the IRR for a project by trial-and-error method, at i = 7%, net PW = -$18, and at i = 10%, the
N4
In computing the IRR for a project by trial-and-error method, at i = 7%, net PW = -$18, and at i = 10%, the net PW = $9. What is the best estimate for the IRR? O A. 8.5% O B. 8% O C. 9% O D. 7.75%Step by Step Solution