Narayna Construction Corporation was contracted to build a new retail complex in a small town in northern Saskatchewan for $6,380,000. Construction activities are summarized below
Narayna Construction Corporation was contracted to build a new retail complex in a small town in northern Saskatchewan for $6,380,000. Construction activities are summarized below by year:
20X2 | 20X3 | 20X4 | |
Costs incurred during the year | 1,702,000 | 1,786,000 | 3,062,083 |
Estimated cost to complete | 3,401,000 | 3,019,500 | 0 |
Required:
1. Prepare the journal entries for revenue recognition for each year. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field. Do not round intermediate calculations. Round your final answers to the nearest whole dollar.)
No | Date | General Journal | Debit | Credit |
---|---|---|---|---|
1 | 20X2 | Contract Asset | ||
Cash | ||||
2 | 20X2 | Cash | ||
Revenue | ||||
3 | 20X2 | Construction costs | ||
Contract Costs | ||||
4 | 20X3 | Contract Costs | ||
Cash | ||||
5 | 20X3 | Cash | ||
Revenue | ||||
6 | 20X3 | Construction costs | ||
Contract Costs | ||||
7 | 20X4 | Contract Asset | ||
Cash | ||||
8 | 20X4 | Cash | ||
Revenue | ||||
9 | 20X4 | Construction costs | ||
Contract Costs |
2. Calculate the gross margin for each year on the contract. (Negative amounts should be indicated by a minus sign.)
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started