Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Need help in building a Project WBS, as I have done the project charter for this already and will send that below. Here are the

Need help in building a Project WBS, as I have done the project charter for this already and will send that below. Here are the details:

The purpose of this to: Determine the work required to build Mamma Mia's IT system (Case Study). List all deliverable end items in the form of Summary Tasks. Define and list sub-tasks under each Summary Task. Produce a final WBS.

At this stage, the Project WBS should not include: Duration estimates (just leave it at the "1d" default value) Predecessor-successor links (aka dependencies) Resource data (cost, names, etc.). Project Work Breakdown Structure Here are some Level 2 WBS elements you should include (among others), not necessarily in the order shown: IT System Design System Hardware System Software System Networking System Test Project Management System Transition

With respect to hardware, software, and networking - lower level WBS elements will deal with Orders, Delivery, Receiving, Installation, etc. Make sure that your WBS (and .mpp file) include the following tasks as part of your WBS. These are necessary but more tasks may well be needed. This also does not mean that a single task will necessarily suffice for each of these. Rather, include as many tasks as it takes to do the job, but please include at least the following kinds of tasks in addition to whatever else you were planning for your WBS:

Ordering, and receiving hardware Ordering, and receiving software Ordering, and receiving networking Installing hardware Installing software Installing networking Managing, controlling, and monitoring the project and the team Project status reports

There is a lot more to the WBS than this. Do not spend too much time getting "down into the weeds". A good size for this class would be no more than 10 Level 2 elements. Decompose these to Level 3 elements (or Level 4 if absolutely necessary). Remember, the lowest level elements (those with indented sub-tasks, not indented summary tasks) will be your work packages. Finally, define and list sub-tasks within each work package.

The format for the WBS for what shows is

Indicators (column shows ) Task Mode Constraint Type Constraint Date Outline Level WBS Task Name Duration Start Finish Predecessors Successors Type

Project Charter I have

Implementation of The Shoppe's IT System Project Charter Executive Summary An integrated information technology (IT) system for The Shoppe, owned by Mamma Mia, is being designed, developed, and installed. This document outlines the project strategy and proposal for this project. With the addition of sandwiches, caf seats, and bakery goods, the expansion project intends to make the bakery a more effective and user-friendly business. The suggested IT system will support online ordering, point-of-sale, inventory management, bookkeeping, and payment processing. The objectives, restrictions, team, hazards, communication strategy, change threshold, completion requirements, and finance of the project are all included in this document. Modern, user-friendly, and tailored to Mamma's particular needs, the IT system will be.

Problem Statement The Shoppe's present manual and paper-based procedures are restricting its ability to expand and become more effective. By implementing an integrated IT system, Mamma Mia hopes to increase the size of her bakery, provide additional services, and improve the efficiency of her operational procedures. Significant obstacles stand in the way of attaining these objectives, including a lack of IT expertise and the absence of essential technological infrastructure.

Project Scope The suggested IT system will support online ordering, point-of-sale, inventory management, bookkeeping, and payment processing. The objectives, restrictions, team, hazards, communication strategy, change threshold, completion requirements, and finance of the project are all included in this document. Modern, user-friendly, and tailored to Mamma's particular needs, the IT system will be.

Project Goals: Design and deploy a cutting-edge IT system that is specifically suited to The Shoppe's needs. Make it possible for effective point-of-sale operations, inventory control, and bookkeeping. Support the processing of payments, client relationship management, and online ordering. For Mamma and her staff to use the system effectively, provide training and assistance. Maximize client happiness, revenue growth, and overall corporate efficiency.

Project Management Methodology: A structured methodology will be used for the project's requirements collecting, design, development, testing, training, and deployment. The system's alignment with Mamma Mia's business requirements will be made possible through collaboration. Risk management, milestone reviews, and regular communication will be given top priority throughout the business.

Technical Fix: The suggested IT system will have the following components: Terminals at the point of sale for smooth client transactions. For effective tracking and ordering of goods, use inventory management software. For reliable financial records, use bookkeeping and finance management software. The website has an integrated online ordering mechanism that allows for advance orders. Debit and credit card payment processing capabilities. a user-friendly interface made to be as comfortable for Mamma and her staff as possible.

ROM for the anticipated project schedule and cost: Requirements 2 weeks for gathering Design of the system: 4 weeks 12 weeks for both development and testing 4 weeks for training and deployment Estimated duration overall: six months Costs of the Project (ROM) Assumed: $190,000 Licensing and software: $40,000. Hardware Purchase: $30,000. $15,000 for training and assistance Resources on-site: $10,000 Budget total projected: $95,000

Significant Stakeholder(s): Owner of The Shoppe and the main user of the IT system is Mamma Mia.

Project Roles: Team Member 1 PMO Description Develops Project Plan Manages Stakeholders, project team, risks, project schedule, budget, and any conflicts

Team Member 2 is a UI/UX designer. Gathering and evaluating user requirements, in collaboration with product managers and engineers. Illustrating design ideas using storyboards, process flows and sitemaps. Team Member 3 is a software developer. Design, program, build, deploy and maintain software using many different skills and tools Team Member 4 is Hardware Engineer Research, design, develop, and test computer systems and components such as processors, circuit boards, memory devices, networks, and routers. Team Member 5 is the training coordinator. Responsible for managing, designing, developing, coordinating and conducting all training programs Team Member 6 Quality Assurance Analyst Conduct testing on software, websites, and other technical products to identify and resolve bugs, defects, and other potential issues

Assumptions and Project Restraints Restraints: Budget of $100,000, deadline of six months, lack of networking, limited IT expertisethese are the restrictions.

Assumptions: Mamma's readiness to pick up new skills and adapt to the new IT system; accessibility of necessary technological resources.

Risk Statement in Brief: Risks: Scheduling delays for projects because of unanticipated technological difficulties. During the system implementation, there was employee resistance to change. Integration difficulties with outside systems, such suppliers' and the health departments.

Risk Reduction Techniques: To quickly resolve problems, conduct regular technical evaluations. A thorough training program for staff members to aid changeover. testing in-depth and working with other partners to ensure seamless integration.

Plan for Initial Communications: Mamma Mia and weekly project status conferences. team standups every two weeks to talk about accomplishments and problems. Monthly project status updates that list accomplishments and approaching deadlines. Change Threshold: Any modifications that materially affect budget, availability of resources, or timeline will need the creation of a new project charter and require Mamma Mia's consent.

Project completion is defined as the moment the new IT system is completely operational, all staff members have received the necessary training, and the system achieves the set goals. Successful integration with suppliers, operational online ordering, payment processing, and efficient point-of-sale operations are among the completion requirements.

We, the undersigned, accept the conditions and goals stated in this project charter: Mamma Mia (Sign) Date: _______________ Manager of the project Date: _______________

Final Remarks: The Shoppe will become a more contemporary and effective business thanks to the suggested IT system. Throughout the project, Mamma Mia's involvement will be essential to ensure that it is in line with her requirements. The project team provides an affordable and user-friendly solution. Mamma's budget of $100,000 and the expected budget of $95,000 are in line. Within the allotted six months, the project will be finished.

Please study this Project Charter and offer any clarifications or comments required to move the project forward. Your participation and feedback are crucial for the new IT system's effective deployment.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Frank Rothaermel

5th Edition

126026128X, 978-1260261288

More Books

Students also viewed these General Management questions

Question

What elements of multimedia-based instruction facilitate learning?

Answered: 1 week ago

Question

Food supply

Answered: 1 week ago

Question

Mortality rate

Answered: 1 week ago