Question
Need help with last table The PPC system at ABC Company is run weekly to update the master production schedule (MPS) and MRP records. At
Need help with last table
The PPC system at ABC Company is run weekly to update the master production schedule (MPS) and MRP records. At the start of week 1, the MPS for end products X and Y is:
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Product X | 10 |
| 25 | 5 | 10 |
|
Product Y | 5 | 30 |
| 20 |
| 20 |
One unit of component C is required to manufacture one unit of either end product X or Y. Purchasing lead time for Component C is two weeks, and order quantity of 40 units is used, and no (zero) safety stock is maintained for this item. Inventory balance for component C is 25 units at the start of week 1, and theres an open order (scheduled receipt) for 40 units due to be delivered at the beginning of week 1.
Complete the MRP record for component C as it would appear at the beginning of week 1.
Week | 1 | 2 | 3 | 4 | 5 | 6 |
Gross Requirements | 15 | 30 | 25 | 25 | 10 | 20 |
Scheduled Receipts | 40 | 0 | 0 | 0 | 0 | 0 |
Projected Available Balance | 50 | 20 | 35 | 10 | 0 | 20 |
Planned Order Receipts | 0 | 0 | 40 | 0 | 0 | 40 |
Planned Order Releases | 40 | 0 | 0 | 40 | 0 | 0 |
During week 1, the following transactions occurred for component C:
- The open order for 40 units due to be received at the start of week 1 was received on Monday of week 1 with a quantity of 35 (5 units of component C were scrapped on this order).
- An inventory cycle count during week 1 revealed that ten units of component C were missing. Thus, an inventory adjustment of -10 was processed.
- Five units of component C were actually disbursed (instead of the 15 units planned for disbursement to produce end products X and Y). (The MPS quantity of 10 in week 1 for product X was canceled as a result of a customer order cancellation.)
- The MPS quantities for week 7 include 20 units for product X and 10 units for product Y.
- Because of a change in customer order requirements, marketing has requested that the MPS quantity of 5 units for product X scheduled in week 4 be moved to week 3.
- An order for 40 units was released.
Given this information, complete the MRP record for component C as it would appear at the beginning of week 2:
Week | 2 | 3 | 4 | 5 | 6 | 7 |
Gross Requirements |
|
|
|
|
|
|
Scheduled Receipts |
|
|
|
|
|
|
Projected Available Balance |
|
|
|
|
|
|
Planned Order Receipts |
|
|
|
|
|
|
Planned Order Releases |
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started