Need to solve this question professionally ; Thanks Task Examine the following network diagram (duration in weeks) and answer the questions that follow: D=3 2

Need to solve this question professionally ; Thanks

image text in transcribed
Task Examine the following network diagram (duration in weeks) and answer the questions that follow: D=3 2 A=6 E=4 F=& J=6 1 B=4 K=7 6 8 C=3 H=8 L=6 4 1=5 Required: 1. Draw a new precedence (AON) network diagram and compute and indicate on the diagram Early Start, Early Finish, Late Start, and Late Finish times for each activity. (15 pts.) 2. Based on the diagram created in (1) above, compute (a) Free Slack and (b) Total Slack for each activity, and organize your answers on a table (12 prs.) 3. Based on your answers in (2) above, identify the activities that provide scheduling flexibility (3 prs.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Marketing Hospitality

Authors: Cathy H C Hsu, Tom Powers, Thomas F Powers

3rd Edition

0471348856, 9780471348856

More Books

Students also viewed these General Management questions

Question

What does the slope in a simple linear regression model measure?

Answered: 1 week ago

Question

14. Now reconcile what you answered to problem 15 with problem 13.

Answered: 1 week ago