Neo EV is an electrical bus manufacturer headquartered in California. Based on historical sales data and committed contracts, the forecast team estimates that sales in

Neo EV is an electrical bus manufacturer headquartered in California. Based on historical sales data and
committed contracts, the forecast team estimates that sales in 2021 will be as follows:
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Demand 202020203040403020202020
Assembly of an electrical car requires a battery unit that can be manufactured by the company itself. Initially, the factory has 20 workers on the payroll. The company can hire as many new workers as it wants in any month in 2021, with a hiring cost of $4,000 per worker (interviewing and training), whereas the company can fire workers at most once in 2021 due to a requirement of the union contract, with a firing cost of $15,000 per worker (i.e., severance pay).
Assume that, for all workers (regardless of whether the worker is newly hired or not), the monthly wage is $5,000 per worker on the payroll, and, on average, a worker can produce one battery unit in a month. Production cost of a battery unit is $100,000.
In addition, Neo EV has signed a contract with a battery supplier, BXD, in Asia, which enables the former to expedite replenishment of batteries from the latter at a variable cost of $105,000. BXD charges Neo EV a fixed fee (expedite shipping and handling) of $120,000 per order. Assume that Neo EV can decide whether to place an order or not in each month. Inventory costs of unused batteries are counted at the end of each month and have been estimated to be $2,000 per month per unit. Assume zero inventory initially.
The objective is to minimize the total cost, including workers wage, hiring, and firing costs, production costs, inventory costs, as well as purchasing and ordering costs from the outside supplier. Build an Integer Programming spreadsheet model (with binary variables if needed). Note that the number of workers and batteries must be in integers.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Project Management Made Simple

Authors: Terry Schmidt

1st Edition

0470411589, 978-0470411582

More Books

Students explore these related General Management questions