Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Network Diagram Practice Base your analysis of the following... Network Diagram Practice Base your analysis of the following three projects on the information in the

Network Diagram Practice Base your analysis of the following...

Network Diagram Practice

Base your analysis of the following three projects on the information in the table. Each project has been defined to contain a list of activities/tasks (each identified by letter) along with the immediate predecessor activities and the optimistic, most likely, and pessimistic time estimates (in days) for completion.

Project A:

  1. Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
  2. Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
  3. Calculate and enter the free slack and total slack for each task in the table.
  4. List all paths with durations and identify the critical path.

Task

Predecessor

a

m

b

Normal duration

Free Slack

Total Slack

A

---

3

4

7

B

---

4

6

10

C

A, B

5

8

11

D

A

8

9

12

E

C

7

8

9

Project B:

  1. Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
  2. Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
  3. Calculate and enter the free slack and total slack for each task in the table.
  4. List all paths with durations and identify the critical path.

Task

Predecessor

a

m

b

Normal duration

Free Slack

Total Slack

A

---

4

4

8

B

A

3

4

6

C

B

4

7

10

D

A

6

9

11

E

D

7

10

12

F

E

5

8

12

G

E

6

7

9

H

C

15

16

18

Project C:

  1. Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
  2. Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
  3. Calculate and enter the free slack and total slack for each task in the table.
  4. List all paths with durations and identify the critical path.

Task

Predecessor

a

m

b

Normal duration

Free Slack

Total Slack

A

---

4

4

7

B

---

3

4

5

C

---

4

7

10

D

B, C

6

8

10

E

A

7

9

12

F

D, E

3

4

12

G

C

6

7

9

H

F, G

10

12

15

I

E

14

14

18

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foodservice Management Principles And Practices

Authors: June Payne Palacio, Monica Theis

13th Edition

0133801101, 9780133801101

More Books

Students also viewed these General Management questions

Question

2. Develop a good and lasting relationship

Answered: 1 week ago

Question

1. Avoid conflicts in the relationship

Answered: 1 week ago