Answered step by step
Verified Expert Solution
Question
1 Approved Answer
NETWORK: PERT 1 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A --- 3 5 7 B -
NETWORK: PERT 1 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A --- 3 5 7 B - 2 4 6 C --- 2 3 4 D A 3 4 5 E B 3 5 13 F C 2 4 6 G D,E,F 4 5 6 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections. ] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (6) for the project round off the standard deviation to the nearest hundredth: two decimal places. 4) What is the completion time at 95% and 99% confidence levels? 5) What is the likelihood of this project being completed in more than 16 days? 6) Between 14 and 17 days? Overall SUMMARY (You should provide a Summary) - All work must be clearly shown! (You should provide a Summary- Adjust as necessary) i. GRAPH of Network with ii. TIMES- Show times on network paths ili Critical Path: CP Highlighted on Network and state Slack: X + + ... etc. 2 iv. x Xbar = - V. Sigma =_____(be sure to provide work - round off to 2 decimal places) vi. CI: __% [? - ?]. vii. ND 1: (P x> %. vili. ND 2: (P % CI: _% [? - ?]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started