Question

1 Approved Answer

Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, seven percent; fatigue, six percent; delay, five

Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, seven percent; fatigue, six percent; delay, five percent. Use the Work Measurement Excel template to determine the standard time for this operation.

Work Observation
Element 1 2 3 4 5 6 7 8 9 Performance Rating
A 0.09 0.14 0.06 0.04 0.11 0.09 0.15 0.14 0.15 85%
B 0.24 0.20 0.22 0.23 0.27 0.25 0.28 0.27 0.27 105%
C 0.48 0.52 0.48 0.45 0.47 0.47 0.52 0.48 0.50 115%
D 0.64 0.66 0.63 0.61 0.70 0.68 0.68 0.66 0.73 90%
E 0.71 0.74 0.74 0.68 0.82 0.81 0.79 0.78 0.81 115%
F 1.01 1.04 0.98 1.00 1.09 1.10 1.04 1.07 1.11 90%

Round your answer to two decimal places.

minutes

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions