no bookmarked, confident, or note marked Question 57 : The summation of the costs of the remaining work based on estimates from the project team
no bookmarked, confident, or note marked Question 57 : The summation of the costs of the remaining work based on estimates from the project team members working on these activities is known as which of the following? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Bottom-up ETC option B (BAC -EV) / CPI option C Reestimate option D EAC - A