no explanation needed, just answer please The project baseline is created in which of the following phases of a project? Group of answer choices Execution
no explanation needed, just answer please
The project baseline is created in which of the following phases of a project?
Group of answer choices
Execution
Planning
Initiating
Monitoring and Controlling
Flag question: Question 16
Question 16 1 pts
A project manager is not an expert in any one technical area; they are expected to have a broad management expertise in 10 different categories.
Group of answer choices
True
False
Flag question: Question 17
Question 17 1 pts
____________________ is responsible for helping the IT team translate the business requirement into a technical specification.
Group of answer choices
The Sponsor
The Project Manager
The Business analyst
All of the Functional teams
Flag question: Question 18
Question 18 1 pts
Groups can feel threatened when asked to collaborate with other teams or departments. To help minimize the resistance that can be attributed to this type of collaboration threat, your company decided to publicly acknowledge the critical roles that the group plays within the organization. What was the company trying to accomplish by doing this?
Group of answer choices
Blocking covert behaviors
Reasserting control
Manipulating boundaries
Reinforcing identity and reaffirming legitimacy
Flag question: Question 19
Question 19 1 pts
The Iron triangle constraints refer to the ___________________ of the project.
Group of answer choices
Time, Charter and Stakeholders
Charter, Scope and Stakeholders
Stakeholders, Budget and Resources
Time, Cost and Scope
Flag question: Question 20
Question 20 1 pts
Changes to the project are much more costly at the beginning of the project than at the end of the project.
Group of answer choices
True
False
Flag question: Question 21
Question 21 1 pts
Risk, cost, resource usage do not stay the same over the life of a project.
Group of answer choices
True
False
Flag question: Question 22
Question 22 1 pts
Flash teams are a _______________________________________ .
Group of answer choices
a method marketing used in social media accounts.
way of crowdsourcing and assembling paid experts to complete a project.
method of developing prototypes more efficiently.
method of using unpaid workers through social media.
Flag question: Question 23
Question 23 1 pts
Human crowds do not respond the way bees respond to collective intelligence. The two main factors for this difference are:
Group of answer choices
influence of maladaptive behavior and logical actions
errors of communication and herd mentality
ability to apply logic and reasoning
tendencies toward conformity and copying
Flag question: Question 24
Question 24 1 pts
Sampling of existing documentation, forms, and databases is one technique used to gather business requirements.
Group of answer choices
True
False
Flag question: Question 25
Question 25 1 pts
A Scope Statement is a concise way of including the key elements of the project scope into a sentence or two.
Group of answer choices
Scope Statement
Project Charter Documents
Business Requirements Document
Work Breakdown Structure
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started