Question

00
1 Approved Answer

no image upload show calculation NEED EXPLAINATION dont use chat gpt or any other AI tools otherwise i will check and report your answer and

no image upload show calculation

NEED EXPLAINATION

dont use chat gpt or any other AI tools otherwise i will check and report your answer and your id will revoke permanently and dislike your answer more than 10 acoount so be careful scammers explain answer step by step and unique answer

2a). VAC (Variance at Completion)

You are managing a project that is expected to take 11 months, and the expenses are budgeted to be $1500 per month. 5 months after the project started, you find out that the project is 30% complete and that you have spent $13000.

What is the VAC (Variance at Completion) of the project at this point?

2b). TCPI (To Complete Performance Index)

You are managing a project that is expected to take 10 months, and the expenses are budgeted to be $11500 per month. 2 months after the project started, you find out that the project is 20% complete and that you have spent $11000.

What is the TCPI (To Complete Performance Index) of the project at this point?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these Economics questions