Nodes with __________ must be on a critical path whereas nodes with ________ can be delayed. Group of answer choices no predecessors; no successors positive
Nodes with __________ must be on a critical path whereas nodes with ________ can be delayed. Group of answer choices no predecessors; no successors positive slack; negative slack no successors; no predecessors zero slack; positive slack positive slack; zero slack