Question
Nonuniform Inputs, Weighted Average Carter Inc. had the following production and cost information for its fabrication department during April (with materials added at the beginning
Nonuniform Inputs, Weighted Average
Carter Inc. had the following production and cost information for its fabrication department during April (with materials added at the beginning of the fabrication process):
Production: | |
Units in process, April 1, 50% complete with respect to conversion | 10,000 |
Units completed | 65,200 |
Units in process, April 30, 60% complete | 12,000 |
Costs: | |
Work in process, April 1: | |
Materials | $40,980 |
Conversion costs | 15,900 |
Total | $56,880 |
Current costs: | |
Materials | $125,000 |
Conversion costs | 210,000 |
Total | $335,000 |
Carter uses the weighted average method.
Required:
1. Prepare an equivalent units schedule.
Carter Inc. | |||||
Schedule of Equivalent Units | |||||
(Weighted Average Method) | |||||
Materials | Conversion | ||||
Units completed | fill in the blank | fill in the blank | |||
Add: Units in ending WIP x Percent complete | |||||
fill in the blank | fill in the blank % | fill in the blank | |||
fill in the blank | fill in the blank % | fill in the blank | |||
Equivalent units of output | fill in the blank | fill in the blank |
2. Calculate the unit cost. Round all intermediate calculations and final answer to the nearest cent. $ per unit
3. Calculate the cost of units transferred out and the cost of EWIP. In your calculations round unit cost to the nearest cent and your final answers to the nearest dollar.
Cost transferred out | $ |
Cost of ending work in process | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started